A multi-criteria process for IT project success evaluation–Addressing a
|
||
critical gap in standard practices
|
||
João Carlos Lourenço a , João Varajão b,*
|
||
a
|
||
CEGIST, Instituto Superior Técnico, Universidade de Lisboa, Av. Rovisco Pais 1, 1049-001 Lisboa, Portugal
|
||
b
|
||
Centro ALGORITMI, Universidade do Minho, Campus de Azurém, 4804-533 Guimarães, Portugal
|
||
|
||
|
||
|
||
|
||
A R T I C L E I N F O A B S T R A C T
|
||
|
||
Keywords: The evaluation of project success is widely recognised as valuable for improving IT (Information Technology)
|
||
Project success project performance and impact. However, many processes fail to adequately address the requirements for a
|
||
Project evaluation sound evaluation due to their inherent complexity or by not complying with fundamental practical and theo
|
||
Multi-criteria evaluation
|
||
retical concepts. This paper presents a process that combines a problem structuring method with a multi-criteria
|
||
MACBETH
|
||
Process
|
||
decision analysis approach to evaluate the success of IT projects. Put into practice in the context of a software
|
||
Methodology development project developed for a leading global supplier of technology and services, it offers a new way of
|
||
creating a model for evaluating project success and tackling uncertainty, bringing clarity and consistency to the
|
||
overall assessment process. A strong advantage of this process is that it is theoretically sound and can be easily
|
||
applied to other evaluation problems involving other criteria. It also serves as a call to action for the development
|
||
of formal standards in evaluation processes. Practical pathways to achieve such standardization include
|
||
collaboration through industry consortia, development and adoption of ISO frameworks, and embedding eval
|
||
uation processes within established maturity models. These pathways can foster consistency, comparability, and
|
||
continuous improvement across organizations, paving the way for more robust and transparent evaluation
|
||
practices.
|
||
|
||
|
||
|
||
|
||
1. Introduction Additionally, several errors identified by decision analysis literature
|
||
[12,13] are often made, generating meaningless project success evalu
|
||
The sustainable success of virtually any organisation is strongly ations [14]. Some common mistakes involve not including relevant
|
||
associated with the success of its projects [1]. A key factor for project criteria in the evaluation model, not distinguishing the performance of a
|
||
success is that project managers clearly understand what success means project from its value, assigning weights to evaluation criteria without
|
||
[2], which is usually not the case [3]. Despite different notions about considering the ranges of variation of their performance scales, and
|
||
what constitutes “project success” and the many criteria that can be used making calculations that violate measurement scales’ properties. In
|
||
for evaluation (e.g., cost, time, and performance, among others) [4], a other words, such evaluations are inconsistent with multi-attribute
|
||
project must satisfy its clients to be considered successful [5–8]. value theory (MAVT) and value measurement foundations.
|
||
Given the importance and complexity of the evaluation of projects, Considering these limitations, this research proposes a process that
|
||
companies should define and implement systematic processes for eval combines a problem structuring method with a multi-criteria approach
|
||
uating success to improve project management performance and the for evaluating the success of information technology (IT) projects sup
|
||
impact of deliverables [9]. However, despite the models and techniques ported by a real-world case. This process was developed and applied in
|
||
that are currently available for assessing project success, they are typi the context of a project of GlobalSysMakers (for confidentiality reasons,
|
||
cally challenging to implement for a variety of reasons, notably the the name of the company herein is anonymized), a leading global sup
|
||
complexity caused by using multiple and often conflicting objectives (e. plier of technology and services.
|
||
g., minimise cost and maximise quality), the scarcity of empirical studies In the GlobalSysMakers project, the need for a new process arose
|
||
reporting their genuine use in projects [10], and the fact that practices because the project management team felt that the scoring model
|
||
employed in companies are generally informal and simplistic [11]. initially defined for success assessment, while helpful, lacked accuracy.
|
||
|
||
|
||
* Corresponding author.
|
||
E-mail address: varajao@dsi.uminho.pt (J. Varajão).
|
||
|
||
https://doi.org/10.1016/j.csi.2025.104122
|
||
Received 12 August 2025; Received in revised form 7 November 2025; Accepted 23 December 2025
|
||
Available online 24 December 2025
|
||
0920-5489/© 2025 The Author(s). Published by Elsevier B.V. This is an open access article under the CC BY license (http://creativecommons.org/licenses/by/4.0/).
|
||
J.C. Lourenço and J. Varajão Computer Standards & Interfaces 97 (2026) 104122
|
||
|
||
|
||
Following an appraisal of several methodological alternatives, a new weights of several stakeholders without a discussion obliterates their
|
||
multi-criteria approach combined with a problem structuring method individual differences [26]. Additionally, the “importance of the
|
||
was shown to be the best solution, providing the required precision and criteria” should consider their respective performance ranges; other
|
||
transparency to the process, along with a better understanding of the wise, the resulting weights would be arbitrary [27].
|
||
real meaning of the relative importance of each evaluation criterion. Basar [28] proposes a methodology to evaluate the performance of IT
|
||
This paper describes the process developed in detail so that it can be projects in a fuzzy environment. She first identifies the evaluation
|
||
replicated in other projects. Also, the results are presented and dis criteria using the balanced scorecard method. Second, she determines
|
||
cussed, including contributions to theory and practice. the criteria weights with expert judgments and hesitant fuzzy weights.
|
||
The proposed process, which combines a problem structuring Then, the weights are used to evaluate the performance of IT projects in
|
||
method with a multi-criteria approach for evaluating IT project success, a Turkish company. The weighting process described in this paper is
|
||
offers several theoretical implications. First, it advances the conceptu difficult for a non-expert evaluator to understand. Additionally, the
|
||
alization of project success by integrating both subjective stakeholder quantitative performances of projects on the criteria are systematically
|
||
perspectives and objective performance criteria, addressing the multi normalised to scores between 0 and 1 with a linear transformation that
|
||
dimensional and context-dependent nature of success in IT projects. may not correspond to the preferences of evaluators (which may be
|
||
Second, it contributes to decision theory and project management non-linear). The paper does not explain how to address the evaluation of
|
||
literature by demonstrating how problem structuring methods—typi the qualitative criteria.
|
||
cally underutilized in IT evaluation—can enhance the clarity and rele Ismail [29] applies the Delphi method and conducts a seminar with
|
||
vance of criteria selection and prioritization. Third, the integration of experts to identify a construction project’s potential evaluation criteria
|
||
these methodologies provides a foundation for developing more robust, and group them into clusters. A relative importance index is calculated
|
||
transparent, and adaptable evaluation frameworks, which can inform for each criterion with a weighted average of the responses to a survey
|
||
future theoretical models and empirical studies. Ultimately, this expressed on a Likert scale. In a subsequent step, the experts 1) reduced
|
||
research supports the movement toward standardization by offering a the number of clusters and criteria and 2) assigned the same weight to
|
||
replicable and theoretically grounded process that can be refined and the latter. Then, a priority index was calculated for each criterion with
|
||
generalized across different organizational and project contexts. the Priority Evaluation Model (PEM) [30], which combines the “satis
|
||
The remainder of this paper is organised as follows. Section 2 briefly faction” rate (assigned by the experts) and the “importance” of the cri
|
||
reviews previous related work on project evaluation methods, cases, and terion. The overall project success is obtained with a weighted sum of
|
||
multi-criteria evaluation methods. Section 3 describes the case context the averages of the priority indexes obtained on each cluster and the
|
||
and the development of the success evaluation model using a process clusters’ weights. However, the paper does not explain how these
|
||
that combines a problem structuring model with a multi-criteria deci weights were assessed. Additionally, the Likert scale classifications
|
||
sion analysis approach. Section 4 discusses the results obtained. Finally, cannot be used for calculating averages or other arithmetic calculations.
|
||
Section 5 presents the conclusions and avenues for further work. Nguvulu et al. [31] use a Deep Belief Network (DBN) to evaluate eight
|
||
IT projects’ performances after training the DBN with five projects of 12
|
||
2. Previous related work months duration. The DPN automatically assigned weights and scores to
|
||
the criteria, considering possible interactions between them. The au
|
||
2.1. Success of projects thors stress the advantage of this approach by not considering human
|
||
subjectivity. However, from our point of view, this is a weakness
|
||
Evaluation can be defined as the assessment and analysis of the ef because the subjective preferences of project managers, clients, and
|
||
ficiency and effectiveness of the project’s activities and results. The other stakeholders should be considered in an evaluation process to
|
||
evaluation looks at what is planned to do, what has been achieved, and avoid arbitrary results generated by inadequate analytical approaches.
|
||
how it has been achieved [15]. Kahan and Goodstadt [16] conceive Wohlin and Andrews [32] apply principal component analysis and
|
||
evaluation as a set of questions and methods properly articulated to subjective evaluation factors to estimate which projects are successful or
|
||
review processes, activities, and strategies to achieve better results. unsuccessful out of a set of projects. This statistical approach may be
|
||
Therefore, the purpose of an evaluation is not just to find out what used to identify key project characteristics, but it does not allow for
|
||
happened but to use that information to make the project better [17,18]. evaluating the project’s success according to stakeholders’ preferences.
|
||
There are several evaluation approaches in the literature, some Yan [33] suggests the combined use of the balanced scorecard (BSC)
|
||
considerably complex regarding their practical operationalisation and [34], the Analytic Hierarchy Process (AHP), and the Fuzzy Comprehensive
|
||
use. Varajão et al. [10] present a comprehensive review of models and Analysis method (FCA), respectively, to construct a performance criteria
|
||
methods for evaluating information systems project success. Some ex system, assess the criteria weights, and obtain an overall evaluation
|
||
amples are described and analysed next. score. The author explains how to obtain the performance criteria sys
|
||
Bannerman and Thorogood [19] propose a framework for defining IT tem, but does not explain the weighting and scoring components.
|
||
project success that provides a common language for communication Yang et al. [35] apply a multi-criteria model for evaluating a soft
|
||
and compares what stakeholders perceive as important. The authors list ware development project’s success using the Analytical Network Process
|
||
the criteria that should be used to assess the success of a project within (ANP) [36] to assess the criteria weights at several hierarchical levels.
|
||
five domains (process, project management, product, business, and The scores of a project on a given criterion were obtained by calculating
|
||
strategy). However, they do not explain how to consider these domains the average of the scores assigned by five experts using a 5-point Likert
|
||
and criteria together. scale. Note that, as mentioned above, averages should not be calculated
|
||
Barclay and Osei-Bryson [20] describe a structured framework with ordinal scales. In addition, ANP is based on AHP, a method with
|
||
named Project Objectives Measurement Model (POMM) to identify the known issues that affect the validity of the criteria weights (see, e.g.,
|
||
criteria for evaluating an information system (IS) project and assigning a [37–39]).
|
||
performance measure to each criterion. POMM applies value-focused Section 2.2 reviews important concepts and methods related to
|
||
thinking principles [21] and goal question metric methods [22]. An multi-criteria evaluation that are needed to create a proper value mea
|
||
illustrative case is presented in which the importance of each criterion is surement model [40,41] to assess the success of a project.
|
||
directly assessed using an average of the stakeholders’ answers based on
|
||
a 5-point Likert scale. However, despite its virtues, this operation is 2.2. Multi-criteria evaluation
|
||
neither quantitatively nor substantively meaningful [23], respectively,
|
||
because a Likert scale is an ordinal scale [24,25] and averaging the In a multi-criteria value model, the measure of success of a project is
|
||
|
||
2
|
||
J.C. Lourenço and J. Varajão Computer Standards & Interfaces 97 (2026) 104122
|
||
|
||
|
||
given by the additive value function model: generates a proposal of weights compatible with the inputted qualitative
|
||
n n
|
||
judgments by solving the linear programming problem described in
|
||
∑ ( ) ∑
|
||
V(x1 , x2 , …, xn ) = wj vj xj , with wj = 1 and wj > 0, ∀j (1) Bana e Costa et al. [52]. The evaluators should validate the proposed
|
||
j=1 j=1 weighting scale and adjust it if needed.
|
||
|
||
Where V is the overall value score of the success of the project, wj is the 2.2.2. Methods to build value scales
|
||
weight of criterion j, vj(xj) is the value score on criterion j of the per We must assign fixed scores to the previously defined references to
|
||
formance xj, and nrepresents the number of evaluation criteria. build a criterion value scale. For example, we may assign 100 and
|
||
Despite being straightforward in form, this model is often poorly 0 value units to the “best” and the “worst” performances in each crite
|
||
applied. We highlight that the criteria weights wj are scaling constants rion, respectively, although two other scores could be used so that the
|
||
[42], which represent trade-offs between criteria and not the erroneous highest score is assigned to the most preferred reference. Though this
|
||
notion of criteria’s measures of importance [21]. In addition, vj is a arbitrary assignment of scores leads to obtaining interval value scales
|
||
measurable value function, which represents both a preference order [25]. Additionally, the score of a project on a given criterion should
|
||
between performances on criterion j and a strength-of-preference order consider the preferences expressed by the evaluators upon performance
|
||
on differences of performances [43]. Moreover, the model requires the ranges within the criterion [43] (e.g., the difference in value between
|
||
criteria to be mutually preferentially independent [44], which entails performances A and B is worth twice the difference between C and D).
|
||
special care during the model structuring phase. Hereinafter, we present two numerical scoring methods and a qualita
|
||
There are some fundamental aspects to note regarding the desired tive one.
|
||
properties for each evaluation criterion and also for the whole set of Edwards [53] presents the direct rating method. This numerical
|
||
criteria [45]. Each criterion should be essential for the evaluation and procedure first requires evaluators to rank the project performances in
|
||
controllable in the sense that the performance of the project influences order of decreasing attractiveness. The highest score (100 units) is
|
||
the degree to which the criterion is satisfied, independently of other assigned to the “best” performance and the lowest score (0 units) to the
|
||
additional decisions. Also, a family of evaluation criteria should be: “worst”. Intermediate scores are assigned to other performance levels
|
||
complete (the set of criteria should represent all of the relevant conse considering the intensities of preferences between each two of them,
|
||
quences of the project); nonredundant (the criteria should not repeat the knowing that the difference between the “best” and “worst” is worth 100
|
||
same concerns); concise (the number of criteria should be kept to the value units. This method allows scoring a project directly or indirectly
|
||
necessary minimum to evaluate the project); specific (each criterion using a performance measure (e.g., quantitative continuous, quantita
|
||
should be able to assess the consequences of the project, instead of being tive discrete, or qualitative). von Winterfeldt and Edwards [54] describe
|
||
so broad that it compromises this purpose); and understandable (the the bisection method, also known as the mid-value splitting technique [55],
|
||
evaluation criteria should be clear in the eyes of any interested to create a value scale for a criterion. This numerical method assigns the
|
||
individual). highest score to the “best” performance (100) on the criterion and the
|
||
Depending on the ability to use appropriate numerical principles and lowest score (zero) to the “worst”. Then, it is asked which performance p
|
||
fluency to express oneself in words, an evaluator may prefer to apply a has a value equally distant from the “best” and the “worst” perfor
|
||
numerical method or a non-numerical one [46]. In light of this, the mances, which means that the ranges “p–to–best” and “p–to–worst” have
|
||
remainder of this section focuses on quantitative and qualitative tech the same strength-of-preference. Therefore, the performance p would get
|
||
niques tailored for these two types of evaluators. Specifically, we delve a midpoint score of 50. Similar midpoint questions are asked to identify
|
||
into methods for criteria weighting and building a value scale for each other points that can be used to form a piecewise linear value function or
|
||
criterion. a curve. This method allows the creation of value functions upon a
|
||
quantitative and continuous performance measure on the criterion.
|
||
2.2.1. Weighting methods Bana e Costa and Vansnick [50] developed MACBETH [51] to create
|
||
A theoretically sound weighting method must consider the perfor a value scale for a criterion (and to weight criteria, as described in the
|
||
mance ranges defined by two fixed references on each criterion. Com preceding section). Still, contrary to the above-mentioned methods, it
|
||
mon references are, for example, the “worst” and the “best” needs only to elicit qualitative judgments. An evaluator judges the dif
|
||
performances [39] or “neutral” and “good” performances [47]. Below, ference in attractiveness between two performances at a time, using the
|
||
we briefly describe two quantitative weighting procedures and one qualitative scale presented in the previous section, and inputs them into
|
||
qualitative. the software tool M-MACBETH. This tool verifies the consistency of the
|
||
Keeney and Raiffa [48] developed the trade-off procedure, which is a inputted judgments and generates a proposal of a value scale compatible
|
||
numerical method that requires establishing indifferences between two with them and with the scores assigned to the reference performances
|
||
fictitious projects using two criteria at each time. After establishing n – 1 “best” and “worst” (or “good” and “neutral”) [52]. In the final step, the
|
||
indifference relationships for the n criteria, a system of equations is evaluator must validate and adjust the proposed value scale if needed.
|
||
solved, including one equation in which the sum of the weights equals 1, As in direct rating, this method allows scoring a project directly or
|
||
to obtain the criteria weights. indirectly using any performance measure.
|
||
Edwards and Barron [49] created the swing weighting method, which
|
||
is a numerical method that involves measuring the relative importance 2.3. Review summary
|
||
of the improvements (swings) that can be achieved on the criteria,
|
||
considering a change from the “worst” to the “best” performance on In the project success literature reviewed, most papers address the
|
||
each of them. identification of IT criteria (e.g., Lobato et al. [4] and Assalaarachchi
|
||
Bana e Costa and Vansnick [50] developed MACBETH [51] to weight et al. [56]) or success factors (e.g., Pinheiro et al. [57] and Jayakody and
|
||
the criteria. This procedure requires ranking the worst–best swings and Wijayanayake [58]), but only a few present an evaluation approach. In
|
||
judging them using the qualitative scale of difference in attractiveness: addition, the evaluation methods identified suffer from one or more
|
||
no (difference), very weak, weak, moderate, strong, very strong, or extreme. theoretical errors (e.g., weights used as indicators of importance, aver
|
||
This qualitative scale is also used to judge the difference in attractive ages calculated with ordinal scales, application of techniques with
|
||
ness between two swings at a time. The elicited judgments are used to fill known flaws, and normalisation procedures that do not consider
|
||
in the upper triangular part of a matrix in the software tool non-linear preferences). Furthermore, as far as we know, there is no
|
||
M-MACBETH, which validates each judgment’s consistency with those description of a formal process that may guide the evaluators from
|
||
previously inputted (see [52], pp. 425–443). Then, the software tool beginning to end, i.e., from identifying the evaluation criteria until
|
||
|
||
3
|
||
J.C. Lourenço and J. Varajão Computer Standards & Interfaces 97 (2026) 104122
|
||
|
||
|
||
reaching an overall measure of project success. Therefore, a gap in the IT different roles in the project; all of them were somehow interested in the
|
||
project literature needs to be addressed, which will be done by applying project’s outcomes. The group had three members: two from TEAMGSM
|
||
multi-criteria evaluation principles. and TEAMUNI, and one external consultant. The team members were
|
||
Given the characteristics of the evaluators, the simplicity of use of selected considering their managerial responsibilities and to ensure
|
||
the MACBETH method and its software tool M-MACBETH, including its representativeness of all the involved parties. All the members agreed to
|
||
ability to validate the consistency of the value judgments expressed by be involved in the model development tasks. Note that larger groups
|
||
evaluators and to work with any performance measure (be it qualitative require different group processes, typically having separate meetings
|
||
or quantitative, continuous or discrete), this was the approach selected with stakeholders of different areas of interest to develop parts of the
|
||
to weight the criteria and build a value function for each criterion in the model, and with merge meetings gathering higher-level representatives
|
||
real-world case described in this paper. of the client to validate the work done by the stakeholders and to finish
|
||
the overall model [63].
|
||
3. Model development Fig. 1 depicts the model development tasks. The first task involves
|
||
identifying the aspects of interest for evaluating the project’s success
|
||
3.1. Research setting (“problem structuring”, described in Section 3.3). This is a critical task
|
||
because it is not possible to develop a proper evaluation model without
|
||
GlobalSysMakers develops solutions in four business areas: mobility understanding the problem, which is the reason why several publica
|
||
solutions, industrial technology, consumer goods, and energy and tions have been devoted to identifying the fundamental evaluation
|
||
building technology. It has several divisions, including automobile concerns to be addressed (e.g., [28,64]). Second, all the relevant eval
|
||
multimedia, automobile accessories, electric tools, heating and hot uation criteria should be included in the model, and a descriptor of
|
||
water, and home appliances. It employs roughly 410,000 associates performance should be identified for each of them, enabling the
|
||
worldwide, has about 440 subsidiaries and regional companies in 60 assessment of the extent to which each criterion is met (“model struc
|
||
countries, and employs nearly 70,000 associates in research and devel turing”, Section 3.4). Third, the evaluation component of the model must
|
||
opment at 125 locations. be built (“value model building”, Section 3.5), which includes the con
|
||
The target project, here identified as PROJRD, was part of an R&D struction of a value function for each criterion to transform the perfor
|
||
program that had the participation of GlobalSysMakers and a university. mances of the project into value scores (Section 3.5.1), and weighting
|
||
The project had as its primary goal the development of a software tool to the criteria to depict their trade-offs (Section 3.5.2). Last, the evaluation
|
||
automate the assessment of printed circuit boards (PCBs) design. PCBs model should be tested for adequacy and consistency (Section 4.1).
|
||
are essentially boards that connect electronic components used in all
|
||
(but the simplest) electronic products, such as household appliances or
|
||
vehicles. In addition to the software tool, the project deliverables 3.3. Problem structuring
|
||
included technical specifications, prototypes, and presentations.
|
||
The software development process adopted was based on a hybrid/ The problem structuring task aims to identify the fundamental ob
|
||
agile methodology supported by SCRUM [59]. Agile methods for soft jectives [45] that determine the project’s success from the client’s
|
||
ware development have been increasingly used in the IT sector [60] and perspective. Such objectives are essential reasons for the project’s suc
|
||
are now mainstream [61]. In this project, agility enabled greater cess. Therefore, they should be used as criteria in the evaluation model.
|
||
adaptability of the development phases according to the company’s However, the identification of these objectives in ill-structured
|
||
needs and requirements, which evolved along with the project lifecycle. problems may not be easy, which is why we opted to apply a problem
|
||
Thus, it was possible to deal with changes in the requirements that were structuring method (PSM) known as group map [65], which can be used in
|
||
reflected in the final deliverables during the project development. In a combination with a multi-criteria decision analysis approach [66].
|
||
later phase of the project, the SCRUM was coupled with a waterfall To begin structuring the problem, the decision-making group was
|
||
process since the objectives stabilised without needing a periodic up asked to say which aspects or concerns were relevant to evaluate the
|
||
date. The project team was multidisciplinary, incorporating engineers project’s success. Then, for each of the concerns expressed, it was asked,
|
||
from GlobalSysMakers (TEAMGSM) and researchers from the university “Why is that important?” or “What would be the consequences of doing
|
||
(TEAMUNI). Together, the teams (TEAMGSM and TEAMUNI) had that?”, which allowed us to identify other aspects.
|
||
electronics, software engineering, and project management skills. Fig. 2 depicts the complete group causal map built with the answers
|
||
On average, the team allocated 1040 h per month to the project
|
||
(approximately 6.5 Full-Time Equivalent), distributed by the different
|
||
tasks of the project and according to the functions performed by each
|
||
element (three of the team members were not full-time in the project).
|
||
The project had a duration of 36 months.
|
||
The project’s overall success was first assessed using a simple grid
|
||
scoring model built by non-specialists in evaluation, which directly
|
||
scored the project on several criteria and assigned importance weights.
|
||
However, the project management team felt the need for a more
|
||
advanced model to improve confidence in the evaluation. More in-depth
|
||
research on multi-criteria evaluation revealed some misinterpretations
|
||
in that process, which ultimately led to the development of a new model
|
||
in line with decision analysis principles. This paper describes the new
|
||
evaluation model.
|
||
|
||
3.2. Development tasks
|
||
|
||
The model development process started by asking the project man
|
||
ager to identify the members who should form the decision-making
|
||
group [62], i.e., the group in charge of developing the model to eval
|
||
uate the project’s success. It was recommended to select members with Fig. 1. Model development tasks.
|
||
|
||
4
|
||
J.C. Lourenço and J. Varajão Computer Standards & Interfaces 97 (2026) 104122
|
||
|
||
|
||
|
||
|
||
Fig. 2. Group map.
|
||
|
||
|
||
of the elements of the group using the software tool “Decision Explorer”
|
||
(from Banxia Software Ltd., https://banxia.com/dexplore), which
|
||
automatically numbered the concerns for identification purposes. This
|
||
map results from several iterations, adding some aspects and removing
|
||
others. Note that a specific concern may be expressed by one statement
|
||
(e.g., “(33) good requirements definition”) or by two statements sepa
|
||
rated by an ellipsis, which depicts a positive pole and a negative one to
|
||
clarify the meaning of the concern (e.g., “15 time fulfilment… time
|
||
exceeded”). An arrow between two concerns indicates the direction of
|
||
causality. When an arrow points to a concern with two poles, it means
|
||
that the concern affected is the one at the positive pole (e.g., a “(29) good Fig. 3. Project’s success evaluation criteria.
|
||
contract management” contributes to the positive pole of “(1) cost
|
||
fulfilment… cost exceeded”; in the reverse case, the arrow would have a problem structuring task.
|
||
negative sign near its head). The concerns represented by these criteria are as follows:
|
||
In Fig. 2, it is possible to identify chains of means-ends objectives. For
|
||
example, an “(31) effective change management” contributes to the • Scope/quality fulfilment (ScoQual)—the extent to which the planned
|
||
“(36) deliverables use”, which respectively allows to “(41) reduce users’ (functional and non-functional) requirements were fulfilled (this
|
||
repetitive work”, which contributes to “increase users’ satisfaction”. criterion resulted from concern 14 in Fig. 2).
|
||
Although the “(41) reduce users’ repetitive work” is a means-objective
|
||
to the end-objective “(39) increase users’ satisfaction”, the group The prime deliverable of the project is a software tool to support the
|
||
considered the former a fundamental objective because it is important in PCB’s design assessment, the other deliverables being subsidiary to this
|
||
itself and not because of its contribution to the latter. Therefore, “(41) tool. In the end, if the software tool does not comply with a minimum set
|
||
reduce users' repetitive work” will be used as an evaluation criterion. of planned requirements, it will not be able to assess the PCB’s design
|
||
Objective “(39) increase users' satisfaction” was considered too broad to and will compromise the investment objectives.
|
||
evaluate the project’s success and thus will not be used.
|
||
• Cost fulfilment (Cost)—the extent to which the planned cost was
|
||
fulfilled (this criterion resulted from concern 1 in Fig. 2).
|
||
3.4. Model structuring
|
||
The budget defined for the project needs to be carefully managed due
|
||
3.4.1. Evaluation criteria to being financed by an external R&D entity with a very narrow margin
|
||
Fig. 3 depicts the seven evaluation criteria that emerged from the of deviation.
|
||
concerns highlighted in bold in the group causal map developed in the
|
||
|
||
5
|
||
J.C. Lourenço and J. Varajão Computer Standards & Interfaces 97 (2026) 104122
|
||
|
||
|
||
• Time fulfilment (Time)—the extent to which the planned time was direct (the descriptor levels should directly describe the performances on
|
||
fulfilled (this criterion resulted from concern 15 in Fig. 2). the corresponding criterion), operational (the information concerning
|
||
the performances of the project can be obtained and value judgments
|
||
Since this project is part of a large program, time fulfillment is a can be made), understandable (performances and value judgments made
|
||
significant management aspect because all the program’s projects must using the descriptor can be clearly understood and communicated).
|
||
be finished simultaneously due to the program’s constraints. In other Table 1 presents the list of all the descriptors created to measure the
|
||
words, not meeting the deadline in this project would mean completing performance of the project, as well as two reference performance levels,
|
||
it in whatever form it is in when the program reaches its end, complying “neutral” and “good”, for each of them. Note that the definition of two
|
||
or not with the scope, and delivering or not what was planned. reference performance levels is required to weigh the criteria, allowing
|
||
comparisons between criteria preference ranges and defining two fixed
|
||
• Increase of the number and type of errors identified in each verification anchors for the value scales (see Section 2.2). Furthermore, the use of a
|
||
cycle (IncNoType)—the extent to which the number and type of errors “neutral” performance level (which corresponds to a performance that is
|
||
identified in each PCB’s verification cycle increase (this criterion neither positive nor negative on the criterion) and of a “good” perfor
|
||
resulted from concern 43 in Fig. 2). mance level (which corresponds to a very positive performance on the
|
||
criterion) allows to increase the understandability of the criterion, and
|
||
Before the project was implemented in the company, the PCB designs are thus preferable to the “worst” and the “best” references used as ex
|
||
had been checked mainly in a semi-automatic way by specialised engi amples in Section 2.2.
|
||
neers. Due to the many PCB components, details, and rules to review, it As shown in Table 1, the criteria scope/quality fulfilment and increase
|
||
was virtually impossible to check all of the required features. The in the number and type of errors identified in each verification cycle do not
|
||
consequence was the late detection of some errors in more advanced have direct descriptors of performance. For these criteria, constructed
|
||
stages of the projects, or, in other words, in later verification cycles. This descriptors were developed combining the characteristics inherent to
|
||
accounts for the importance of the new software tool to increase the those criteria, as explained next (Bana e Costa et al. [67] describe a
|
||
number and type of errors identified early on in each verification cycle, detailed procedure for creating constructed descriptors).
|
||
thereby reducing the design costs. To measure the performance of the project on the scope/quality
|
||
fulfilment criterion, several requirements that deliver different contri
|
||
• Reduction of the number of verification cycles (RNVC)—the extent to butions to the project’s success were considered, following the MoSCoW
|
||
which the number of verification cycles is reduced (this criterion method principles [68]. These requirements were classified into three
|
||
resulted from concern 37 in Fig. 2). types (“must have”, “important to have”, and “nice to have”) and
|
||
combined to obtain the performance levels of the descriptor presented in
|
||
A PCB typically needs to go through several verification cycles until Table 2.
|
||
it is free from errors and ready for production. When errors are detected To measure the performance of the project on the increase of the
|
||
in a verification cycle, the PCB design needs to be corrected and tested number and type of errors identified in each verification cycle criterion,
|
||
again, possibly requiring a new verification cycle. Each verification several combinations of the number and type of errors identified at each
|
||
cycle of a PCB design implies high costs. Furthermore, there is the risk of verification cycle (based on a past project) need to be considered (see
|
||
detecting errors only at the production stage, with even more severe Table 3). For example, a “5 % increase in the number of identified er
|
||
consequences. A primary expected result of the new software tool is to rors” and a “10 % increase in the type of identified errors” is a perfor
|
||
reduce the number of verification cycles by enabling the early detection mance depicted as level “E5 T10”. A verification cycle includes a series
|
||
of errors. of tests to check for errors in the PCB’s design or if it is ready for pro
|
||
duction (free from errors).
|
||
• Improve efficiency (ImpEff)—the extent to which the number of We note that the indicators used in the constructed scales presented
|
||
verified rules increases in each verification cycle without increasing in Tables 2 and 3 cannot be considered in isolation, as they are mutually
|
||
the involved human resources (this criterion resulted from concern preferentially dependent. For example, in Table 3, an increase of 10 % in
|
||
42 in Fig. 2).
|
||
|
||
Since the process for verifying the PCB’s design rules is semi- Table 1
|
||
automatic, with a substantial part of manual labour, the current num Descriptors of performance.
|
||
ber of specialised engineers can only check some of the relevant aspects. Criterion Descriptor Neutral Good
|
||
With the new software tool, it is expected that the same number of en
|
||
Scope/quality fulfilment Constructed L2 L3
|
||
gineers can check a greater number of design rules, not spending more (ScoQual) descriptor (see
|
||
time doing it. Table 2)
|
||
Cost fulfilment (Cost) Cost of the project Planned 95 % of the
|
||
• Reduction of the repetitive work of the users (RRWU)—the extent to (k€) cost planned cost
|
||
(k€ 500) (k€ 450)
|
||
which the number of rules manually verified is reduced in each Time fulfilment (Time) Project duration Planned 95 % of the
|
||
verification cycle (this criterion resulted from concern 41 in Fig. 2). (weeks) time planned time
|
||
(96 (90 weeks)
|
||
In the semi-automatic verification of PCB’s design rules, manual la weeks)
|
||
Increase in the number and Constructed E5 T0 E10 T5
|
||
bour is repetitive and prone to errors due to the fatigue of specialists.
|
||
type of errors identified in descriptor (see
|
||
Automating most of the rules’ assessment is expected to reduce the re each verification cycle Table 3)
|
||
petitive work of these specialists and free them to perform other tasks. (IncNoType)
|
||
Reduction of the number of Number of 1 cycle 2 cycles
|
||
3.4.2. Descriptors of performance verification cycles verification cycles
|
||
(RNVC) decreased
|
||
In this task, we associate a descriptor of performance with each Improve efficiency (ImpEff) Number of verified 0% 40 %
|
||
evaluation criterion to measure how much the project satisfies the cri rules increased ( %)
|
||
terion. According to Keeney [45], a descriptor should be unambiguous (to Reduction of the repetitive Number of rules 0% 10 %
|
||
describe the performances on the associated criterion clearly), compre work of the users (RRWU) manually verified
|
||
reduced ( %)
|
||
hensive (to cover the range of possible performances on the criterion),
|
||
|
||
6
|
||
J.C. Lourenço and J. Varajão Computer Standards & Interfaces 97 (2026) 104122
|
||
|
||
|
||
Table 2 scope/quality fulfilment criterion with a discrete descriptor, and time
|
||
Scale for “scope/quality fulfilment” criterion. fulfilment criterion with a continuous descriptor.
|
||
Performance levels Fig. 4 presents the matrix of judgments for the scope/quality fulfilment
|
||
criterion. Table 2 shows the constructed descriptor for this criterion
|
||
The project…
|
||
…satisfied all the requirements “must have” and “important to have” L1 where: L1 means “the project satisfied all the requirements ‘must have’
|
||
and most of the “nice to have” and ‘important to have’ and the majority of the ‘nice to have’”, L2 means
|
||
…satisfied all the requirements “must have” and at least 85 % of the L2 = Good “the project satisfied all the requirements ‘must have’ and at least 85 %
|
||
“important to have” and at least 20 % of the “nice to have” (or an of the ‘important to have’ and at least 20 % of the ‘nice to have’ (or an
|
||
equivalent performance on the requirements “important to have”
|
||
and “nice to have”)
|
||
equivalent performance)”, and L3 means “the project satisfied all the
|
||
…satisfied all the requirements “must have” and at least 60 % of the L3 = requirements ‘must have’ and at least 60 % of the ‘important to have’
|
||
“important to have” and at least 20 % of the “nice to have” (or an Neutral and at least 20 % of the ‘nice to have’ (or an equivalent performance)”.
|
||
equivalent performance on the requirements “important to have” We can see in Fig. 4 that the difference in attractiveness between “L1”
|
||
and “nice to have”)
|
||
and “L2 = Good” was deemed weak by the evaluators, whereas the
|
||
…did not satisfy one requirement “must have”, or satisfied less than 60 L4
|
||
% of the requirements “important to have” difference in attractiveness between “L2 = Good” and “L3 = Neutral”
|
||
…did not satisfy more than one requirement “must have” L5 was considered moderate. Therefore, the difference in value between
|
||
“L1” and “L2 = Good” should be lower than the difference between “L2
|
||
= Good” and “L3 = Neutral”, which can be confirmed in the value scale
|
||
Table 3 presented in Fig. 6a, where the former difference corresponds to 65
|
||
Constructed scale for “increase of the number and type of errors identified in value units and the latter to 100.
|
||
each verification cycle” criterion. The time fulfilment criterion has the descriptor of performance
|
||
Increase in the number of Increase in the type of Level
|
||
“project duration (in weeks)” with the references “96 weeks = Neutral”
|
||
identified errors (E) identified errors (T) and “90 weeks = Good”. To build a value function for this criterion, first,
|
||
we created three more equally spaced performance levels: one worse
|
||
10 % 10 % E10 T10
|
||
10 % 5% E10 T5 = than “neutral” (99 weeks), one between “neutral” and “good” (93
|
||
Good weeks), and one better than “good” (87 weeks). Then, the evaluators
|
||
10 % 0% E10 T0 judged the differences in attractiveness between each two of these
|
||
5% 10 % E5 T10 levels, together with the “neutral” and the “good” levels, resulting in the
|
||
5% 5% E5 T5
|
||
5% 0% E5 T0 =
|
||
matrix of judgments presented in Fig. 5.
|
||
Neutral Looking at the diagonal (above the grey shaded cells) of the matrix in
|
||
0% 0% E0 T0 Fig. 5 we see that the intensities of the differences in attractiveness
|
||
between each two consecutive levels increase more when the number of
|
||
weeks exceeds 93 weeks: the evaluators considered weak the differences
|
||
the number of identified errors (E) is valued more highly when the per
|
||
in attractiveness between “87” and “90 = Good” (and also between “90
|
||
centage increase in the type of identified errors (T) is greater. Otherwise, the
|
||
= Good” and “93”), whereas they considered moderate the difference in
|
||
number and the type of identified errors could have been used as in
|
||
attractiveness between “93” and “96 = Neutral”, and very strong the
|
||
dicators for two separate evaluation criteria.
|
||
difference between “96 = Neutral” and “99”. Therefore, the difference in
|
||
After the seven criteria had been clearly identified and their de
|
||
value between “87” and “90 = Good” (and also between “90 = Good”
|
||
scriptors of performance established, the decision-making group was
|
||
and “93”) should be lower than the difference in value between “93” and
|
||
asked whether there was any additional aspect that might be considered
|
||
“96 = Neutral”, and the latter should also be lower than the difference in
|
||
in assessing the project’s success. The negative response indicated that
|
||
value between “96 = Neutral” and “99”, which can be confirmed in the
|
||
this set of criteria was exhaustive and, consequently, that the value tree
|
||
value function presented in Fig. 6c (each of the first two intervals cor
|
||
presented in Fig. 3 could be considered complete.
|
||
responds to 40 value units, whereas the third and fourth equal 60 value
|
||
units and 160, respectively). Therefore, this function shows that the
|
||
3.5. Value model building evaluators considered that increments in time after 93 weeks are
|
||
increasingly penalizing for the project’s success.
|
||
3.5.1. Value functions We emphasize that the decision group made these judgments for
|
||
As previously described, a descriptor of performance provides a way each criterion independently of the performance levels or the differences
|
||
of measuring the project’s performance on its associated criterion. in attractiveness on the remaining criteria, thereby supporting the
|
||
However, to build a value model, we also need to obtain the value of assumption of mutual preferential independence between criteria.
|
||
each plausible performance of the project (in the form of a value scale or Fig. 6 (6a–6g) presents the value functions of all the evaluation
|
||
value function), which requires knowing the preferences of the evalua criteria.
|
||
tors upon differences in performances on the corresponding criterion.
|
||
For that purpose, we applied the MACBETH method [51]. As 3.5.2. Criteria weighting
|
||
described in Section 2.2, the questioning procedure of MACBETH re Weighting requires establishing trade-offs between criteria, which is
|
||
quires the evaluators to answer questions of difference in attractiveness typically demanding because it implies comparing performance im
|
||
between two performance levels at each time, using the qualitative provements on different criteria. The improvements (swings) are defined
|
||
scale: no (difference in attractiveness), very weak, weak, moderate, between the two predefined performance references, “neutral” and
|
||
strong, very strong, and extreme. The answers provided are used for “good”, in each criterion.
|
||
filling in a matrix of judgments in the M-MACBETH software tool, which According to the MACBETH weighting procedure, the first step was
|
||
analyses the consistency of the answers as soon as they are inserted, and to rank the “neutral–good” swings in order of decreasing preference
|
||
then generates (by linear programming) a proposal of value scale which (Fig. 7). The evaluators considered the swing from “1 to 2 verification
|
||
is compatible with the answers provided, given the fixed value scores cycles decreased” as the most important one (1st in Fig. 7), which im
|
||
assigned to the “neutral” and the “good” performances (0 and 100 value plies that the criterion “reduction of the number of verification cycles
|
||
units, respectively). (RNVC)” will have the highest weight. In contrast, the criterion
|
||
We present two examples of applying the MACBETH method to build “reduction of repetitive work of the users (RRWU)” will obtain the
|
||
value functions for criteria with different descriptors of performance: lowest weight because it has the least important “neutral–good” swing
|
||
|
||
7
|
||
J.C. Lourenço and J. Varajão Computer Standards & Interfaces 97 (2026) 104122
|
||
|
||
|
||
|
||
|
||
Fig. 4. MACBETH judgment matrix for the “Scope/quality fulfilment” criterion.
|
||
|
||
|
||
|
||
|
||
Fig. 5. MACBETH judgment matrix for the “time fulfilment” criterion.
|
||
|
||
|
||
(7th in Fig. 7). criteria, because their performances are not worse than “neutral” in any
|
||
In the second step, the improvements provided by the criteria swings of the criteria and are better than it in several criteria. Therefore, both
|
||
were judged qualitatively using the MACBETH semantic scale (Fig. 8), scenarios dominate [69] a “neutral project”. Additionally, we may see
|
||
which allowed filling in the rightmost column in Fig. 9. For example, the that scenario “PCB red 2 cycles” has an overall score very close to that of
|
||
improvement provided by the most important swing [RNVC] was a “good project” (100 units), whereas the value of scenario “PCB red 1
|
||
considered extreme, whereas the least important “neutral–good” swing cycle” is almost mid-distance from a “neutral project” and a “good
|
||
[RRWU] was judged weak. project”.
|
||
Then, the differences in attractiveness between each two “neu However, it is not robust to say that the scenario “PCB no red of
|
||
tral–good” swings were assessed to fill in the remaining cells of the first cycles” corresponds to an unsuccessful project, looking only at its overall
|
||
row of the weighting matrix and fill in the diagonal above the shaded value score. We must determine if its overall result will always be worse
|
||
cells in Fig. 9. For example, Fig. 10 depicts the comparison of the than that of a “neutral project” when in the face of the uncertainty
|
||
“neutral–good” swings in the reduction of the number of verification cycles defined for the model parameters (i.e., the value scores and criteria
|
||
(RNVC) criterion and in the increase in the number and type of errors weights). In fact, the evaluators considered it plausible that: a) each
|
||
identified in each verification cycle (IncNoType) criterion, which was criterion weight (wj,j = 1, …, 7) may vary within an interval defined by
|
||
( )
|
||
deemed as very strong (v. strong in Fig. 9). The other cells with no the lower and upper limits wj ≤ wj ≤ wj , j = 1, …, 7 shown in Table 6;
|
||
judgments were filled in automatically (by transitiveness) with “P” and b) the value scores of the scenario “PCB no red of cycles” may have
|
||
(positive) judgments by M-MACBETH. ( ) ( )
|
||
plus or minus 5 value units (respectively denoted by vj yj and vj yj ,
|
||
Finally, the software tool applied the linear programming model
|
||
described in Bana e Costa et al. [51] to generate a proposal of a j = 1,…,7) in all the criteria for which this scenario has a performance
|
||
weighting scale consistent with the qualitative judgments expressed in different from “neutral” and “good”, otherwise it will keep 0 and 100,
|
||
the weighting matrix, which were subsequently validated by the eval respectively.
|
||
uators (with some minor adjustments), resulting in the weights pre The linear programming (LP) problem (2) was then used to test
|
||
sented in Fig. 11. whether a “neutral project” additively dominates [70] the scenario “PCB
|
||
no red of cycles”, which would require a negative maxD. The result
|
||
maxD = 9.575denotes that there is at least one combination of plausible
|
||
4. Results and discussion
|
||
scores and weights for which scenario “PCB no red of cycles” has a
|
||
higher overall value than that of a “neutral project”.
|
||
4.1. Model testing and results
|
||
The worst possible overall value for scenario “PCB no red of cycles”
|
||
was also calculated, with the LP problem (3), resulting in minD =
|
||
At this point, the actual performances of the project are already
|
||
–14.10. Therefore, in the face of the uncertainty, the overall value score
|
||
known for most of the criteria, but not for the reduction of the number of
|
||
of scenario “PCB no red of cycles” may vary between –14.10 and 9.575.
|
||
verification cycles (RNVC) criterion, which will only be identified in the
|
||
long term. Therefore, three alternative scenarios were created with 7
|
||
∑ [ ( ) ( )]
|
||
hypothetical future performances on RNCV: no reduction at all (PCB no maxD = wj vj yj − vj neutralj (2)
|
||
j=1
|
||
red cycles), a decrease of one verification cycle (PCB red 1 cycle), and a
|
||
decrease of two verification cycles (PCB red 2 cycles). The performances Subject to:
|
||
of these scenarios are shown in Table 4.
|
||
7
|
||
∑
|
||
Applying the value functions previously defined for each criterion to wj = 1
|
||
the performances presented in Table 4, we obtain the partial and the j=1
|
||
overall value scores of the three scenarios shown in Table 5 using the
|
||
previously assessed criteria weights. wj ≤ wj ≤ wj , j = 1, …, 7
|
||
As seen in Table 5, the most advantageous scenario corresponds to
|
||
[ ( ) ]
|
||
“PCB red 2 cycles” with 94.60 overall value units, followed by “PCB red 7
|
||
∑ ( )
|
||
1 cycle” with 49.60, and “PCB no red of cycles” with –6.65. minD = wj vj yj − vj neutralj (3)
|
||
j=1
|
||
Scenarios “PCB red 2 cycles” and “PCB red 1 cycle” undoubtedly
|
||
denote a successful project independently of the weights assigned to
|
||
|
||
8
|
||
J.C. Lourenço and J. Varajão Computer Standards & Interfaces 97 (2026) 104122
|
||
|
||
|
||
|
||
|
||
Fig. 6. Value functions of criteria: (a) scope/quality fulfilment, (b) cost fulfilment, (c) time fulfilment, (d) increase in the number and type of errors identified in each
|
||
verification cycle, (e) reduction of the number of verification cycles, (f) improve efficiency, (g) reduction of the repetitive work of the users.
|
||
|
||
|
||
|
||
|
||
9
|
||
J.C. Lourenço and J. Varajão Computer Standards & Interfaces 97 (2026) 104122
|
||
|
||
|
||
|
||
|
||
Fig. 7. Neutral–good swings ranking.
|
||
|
||
|
||
|
||
|
||
Fig. 8. Neutral–good swings’ weighting judgments.
|
||
|
||
|
||
|
||
|
||
Fig. 9. MACBETH weighting matrix (the P and I within the matrix respectively mean positive difference in attractiveness and indifference).
|
||
|
||
|
||
subject to:
|
||
|
||
|
||
|
||
10
|
||
J.C. Lourenço and J. Varajão Computer Standards & Interfaces 97 (2026) 104122
|
||
|
||
|
||
members. Therefore, the model has a form and content sufficient to
|
||
evaluate the project’s success [71].
|
||
|
||
5. Discussion
|
||
|
||
The absence of a formal evaluation of project success results in the
|
||
waste of relevant lessons that can be used to enhance project manage
|
||
ment practices [9,72]. This is a strong reason for implementing
|
||
well-structured processes to evaluate project success.
|
||
Any evaluation process should start by identifying the success
|
||
criteria according to the decision-makers’ preferences and systems of
|
||
values, which are inherently subjective. We underscore that an evalua
|
||
tion model has an objective component (factual data) and a subjective
|
||
one (value judgments), which should be independently addressed.
|
||
Therefore, subjectivity is a key component in an evaluation process, but
|
||
it should not be confused with ambiguity, which should be avoided. That
|
||
is why the success evaluation criteria should be carefully identified, and
|
||
a measure of the performance of a project on each of those criteria must
|
||
be operationalised. The “neutral” and “good” references of intrinsic
|
||
value allow identifying the project’s success level.
|
||
Fig. 10. Assessment of the difference in attractiveness between the “neu Throughout the development of the evaluation model, the members
|
||
tral–good” swings in RNVC and IncNoType. of the decision-making group were encouraged to engage in open dis
|
||
cussion whenever differences of opinion arose. This approach enabled a
|
||
better understanding of their points of view and helped the group reach
|
||
an agreement on the way forward.
|
||
In the case described herein, the success of the project may depend
|
||
on the future performance of the reduction of the number of verification
|
||
cycles (RNVC) criterion. With “no reduction of verification cycles”, the
|
||
project may be unsuccessful, with –6.65 overall value units, caused by
|
||
its low performance and corresponding negative score (–125 value
|
||
units) on this criterion. However, as we have seen, given the uncertainty
|
||
defined for the partial value scores and the criteria weights, this scenario
|
||
is not guaranteed to correspond to a negative evaluation. In fact, its
|
||
overall value may vary between –14.10 and 9.575 units.
|
||
With a “reduction of 1 verification cycle”, the project would obtain
|
||
49.60 overall value units, which is nearly a mid-distance evaluation
|
||
between a “good project” and a “neutral project”. With a “reduction of 2
|
||
verification cycles”, the project would obtain 94.60 overall value units,
|
||
Fig. 11. Criteria weights. which is very close to that of a “good project”.
|
||
Developing a transparent evaluation process, such as the one
|
||
7
|
||
∑ described here, will promote the decision-making group’s understand
|
||
wj = 1 ing and acceptance of the results. The participation of the decision-
|
||
j=1 makers in all of the process phases is a key element for this purpose,
|
||
which will allow them to develop a sense of ownership of the model
|
||
wj ≤ wj ≤ wj , j = 1, …, 7 [63]. However, this is not a practice found in the literature related to
|
||
After concluding the robustness analysis, the evaluation group evaluating project success, which offers an opportunity for
|
||
revisited the model and considered that it could deal with all the plau improvement.
|
||
sible performances and adequately considered the value judgments of its The proposed process, which integrates a problem structuring
|
||
|
||
|
||
Table 4
|
||
Performance profiles of the project’s success for the three scenarios.
|
||
Scenario / Criterion ScoQual Cost (k€) Time IncNoType RNVC ImpEff RRWU
|
||
(weeks) ( %) ( %)
|
||
|
||
PCB no red of cycles L2 480 96 E10 T10 No decrease 60 15
|
||
PCB red 1 cycle L2 480 96 E10 T10 Decrease 1 cycle 60 15
|
||
PCB red 2 cycles L2 480 96 E10 T10 Decrease 2 cycles 60 15
|
||
|
||
|
||
|
||
|
||
Table 5
|
||
Value scores of the project success for the three scenarios.
|
||
Scenario / Criterion ScoQual Cost Time IncNoType RNVC ImpEff RRWU Overall value score
|
||
(15 %) (5 %) (8 %) (22 %) (45 %) (3 %) (2 %)
|
||
|
||
PCB no red of cycles 100 40 0 115 –125 150 140 –6.65
|
||
PCB red 1 cycle 100 40 0 115 0 150 140 49.60
|
||
PCB red 2 cycles 100 40 0 115 100 150 140 94.60
|
||
|
||
|
||
11
|
||
J.C. Lourenço and J. Varajão Computer Standards & Interfaces 97 (2026) 104122
|
||
|
||
|
||
Table 6
|
||
Plausible intervals for the criteria weights.
|
||
Criterion ScoQual Cost Time IncNoType RNVC ImpEff RRWU
|
||
|
||
Index (j) 1 2 3 4 5 6 7
|
||
Current weight (wj) 15 % 5% 8% 22 % 45 % 3% 2%
|
||
( )
|
||
Upper limit wj 18 % 7% 10 % 25 % 45 % 4% 2.5 %
|
||
Lower limit (wj ) 12 % 5% 8% 19 % 40 % 3% 2%
|
||
|
||
|
||
|
||
method with a multi-criteria decision analysis (MCDA) approach for encouraging future research to refine, validate, and extend the proposed
|
||
evaluating the success of information technology (IT) projects, offers framework. Ultimately, this work not only enriches theoretical under
|
||
several significant theoretical contributions to the fields of project standing but also provides a foundation for more consistent, transparent,
|
||
management, decision sciences, and IS. First, it advances the conceptual and stakeholder-aligned evaluation practices in the IT project domain.
|
||
understanding of IT project success by addressing its inherently multi
|
||
dimensional and context-dependent nature. Traditional models often 6. Conclusions
|
||
rely on narrow success criteria—such as time, cost, and scope—while
|
||
this research introduces a more holistic and stakeholder-sensitive Evaluating the success of IT projects should be a mandatory project
|
||
framework. By incorporating problem structuring methods, the pro management activity. However, this is not observed in the practice [11,
|
||
cess facilitates the elicitation and organization of the stakeholder per 72]. There are several contributions given by the process herein
|
||
spectives, which are often overlooked or underrepresented in described, which can be easily adapted to other evaluation problems:
|
||
conventional evaluation models. This contributes to theory by empha
|
||
sizing the social and interpretive dimensions of project success, aligning • It shows how a multi-criteria approach may be used to evaluate IT
|
||
with contemporary views that success is not an objective outcome but a (software development) projects while avoiding committing critical
|
||
negotiated construct [73]. mistakes.
|
||
Second, the integration of MCDA techniques provides a rigorous and • It offers a transparent process.
|
||
transparent mechanism for prioritizing and aggregating evaluation • It involves the decision-makers in all of the model development
|
||
criteria, thereby enhancing the methodological robustness of success tasks.
|
||
assessment. This methodological synthesis bridges a gap in the literature • It identifies the fundamental objectives of decision-makers with the
|
||
by demonstrating how qualitative insights from problem structuring can help of a problem structuring method, avoiding ending up solving
|
||
be systematically translated into quantitative decision models. Theo the wrong problem [76].
|
||
retically, this supports the development of hybrid evaluation frame • It allows establishing quantitative and substantive meaningful [23]
|
||
works that are both contextually grounded and analytically sound. trade-offs between criteria (i.e., mathematically valid and unam
|
||
Third, the application of the proposed process in a real-world case adds biguously understood).
|
||
empirical depth to the theoretical model, offering evidence of its prac • It allows the management of the project to focus on what matters for
|
||
tical relevance and adaptability. This empirical grounding strengthens the project’s success.
|
||
the external validity of the framework and encourages further theoret • It can be implemented to evaluate the success of other projects, in
|
||
ical exploration across different organizational and project contexts. similar or different contexts.
|
||
The MACBETH approach has been successfully employed, with • The use of descriptors of performance clarifies what is intended to be
|
||
different nuances and across various processes, to evaluate projects or achieved in each criterion.
|
||
decision alternatives in diverse problem settings and for a wide range of • It distinguishes performance from value, instead of directly attrib
|
||
organizations [74]. The process described in this paper, which combines uting scores to the project, mixing these two components.
|
||
problem structuring with the MACBETH approach and robustness • And, it allows creating value scales adjusted to the preferences of
|
||
analysis, may also be applied in other contexts, subject to the necessary evaluators, upon different types of performance (e.g., qualitative or
|
||
adjustments. quantitative, continuous or discrete).
|
||
Our proposed process can also be scaled to the program or portfolio
|
||
level, although this should be done with caution. In the case presented Additionally, it enables the identification of alternative scenarios to
|
||
here, we applied an additive value function model, which is compen deal with unknown future performances and to test the robustness of the
|
||
satory—meaning that poor performance on one criterion can be offset conclusions considering uncertainties on the model parameters.
|
||
by good performance on others. However, this assumption may not al In the target organization, given the shortcomings recognised in a
|
||
ways hold. In a program or portfolio context, for instance, if a key previous “grid scoring model”, the multi-criteria evaluation model of the
|
||
project performs poorly, that alone may render the entire program or real-world case described in this paper was built during an advanced
|
||
portfolio unsuccessful, regardless of the performance of the remaining stage of the project’s development. This late development can be
|
||
projects. In such cases, a mixed model should be adopted, combining considered a threat to internal validity regarding consistency and a
|
||
classification rules to address the non-compensatory criteria with an limitation since the evaluation model should be built during the plan
|
||
additive component for the compensatory ones. ning phase of a project and revisited during the project development to
|
||
Moreover, the research highlights the absence of standardized ap be improved, if needed, or adjusted to possible changes to the project
|
||
proaches for evaluating IT project success, which has long been a limi aim. Another threat to external validity should also be disclosed.
|
||
tation in both academic and professional domains. Standardization Namely, concerning scalability, further research is needed to test if the
|
||
facilitates the dissemination of knowledge and enhances predictability, proposed process can be scaled or adapted for different project sizes or
|
||
thereby minimizing uncertainty and reducing risk [75]. By proposing a types.
|
||
replicable and adaptable process, the study lays the groundwork for the In future work, it would be interesting to create a process capable of
|
||
development of formalized evaluation standards. This has implications dealing with all project phases, allowing the evaluation of its develop
|
||
for theory-building, as it suggests a pathway toward unifying frag ment and evolution at several milestones, from the project initiation
|
||
mented evaluation practices under a coherent, theoretically informed until its termination. The process described in this paper may be
|
||
model. In doing so, it contributes to the ongoing discourse on stan extended to evaluate project success throughout the project lifecycle.
|
||
dardization in project management and information systems evaluation, This requires developing a model that includes both final and
|
||
|
||
|
||
12
|
||
J.C. Lourenço and J. Varajão Computer Standards & Interfaces 97 (2026) 104122
|
||
|
||
|
||
intermediate objectives (criteria) for measuring project success. The [10] J. Varajão, J.C. Lourenço, J. Gomes, Models and methods for information systems
|
||
project success evaluation–a review and directions for research, Heliyon 8 (12)
|
||
intermediate objectives should be used during project development and
|
||
(2022), https://doi.org/10.1016/j.heliyon.2022.e11977.
|
||
later deactivated by setting their weights to zero and rescaling the [11] J. Varajão, J.Á. Carvalho, Evaluating the success of IS/IT projects: how are
|
||
remaining criteria weights so that they sum to one. Monitoring the companies doing it?, in: Proceedings of the 13th Pre-ICIS International Research
|
||
evolution of a project’s success against a well-defined set of criteria will Workshop on IT Project Management (IRWITPM 2018), San Francisco, USA, 2018.
|
||
[12] R.L. Keeney, Common mistakes in making value trade-offs, Oper. Res. 50 (6)
|
||
allow identifying problems sooner and taking proper measures in time. (2002) 935–945, https://doi.org/10.1287/opre.50.6.935.357.
|
||
Furthermore, the integration of the proposed evaluation process in the [13] J.E. Russo, P.J.H. Schoemaker, Decision Traps: The Ten Barriers to Brilliant
|
||
success management process [77] will add value to the management Decision-Making and How to Overcome Them, Doubleday, 1989.
|
||
[14] S. Lipovetsky, A. Tishler, D. Dvir, A. Shenhar, The relative importance of project
|
||
efforts. success dimensions, R&D Manag. 27 (2) (1997) 97–106, https://doi.org/10.1111/
|
||
Finally, since artificial intelligence technology, especially with the 1467-9310.00047.
|
||
rise of Large Language Models (LLMs), has shown great potential in [15] Shapiro, J. (2005). Monitoring and evaluation. C.-W. A. f. C. Participation. htt
|
||
ps://www.civicus.org/view/media/Monitoring%20and%20Evaluation.pdf.
|
||
revolutionizing the automation of various complex tasks [78], it is [16] Kahan, B., & Goodstadt, M. (2005). The IDM manual: basics. http://sites.utoronto.
|
||
imperative to explore it in the context of success evaluation. ca/chp/download/IDMmanual/IDM_basics_dist05.pdf.
|
||
[17] V. Arumugam, J. Antony, M. Kumar, Linking learning and knowledge creation to
|
||
project success in Six Sigma projects: an empirical investigation, Int. J. Prod. Econ.
|
||
CRediT authorship contribution statement 141 (1) (2013) 388–402, https://doi.org/10.1016/j.ijpe.2012.09.003.
|
||
[18] R. Linzalone, G. Schiuma, A review of program and project evaluation models,
|
||
João Carlos Lourenço: Writing – review & editing, Writing – orig Meas. Bus. Excell. 19 (3) (2015) 90–99, https://doi.org/10.1108/MBE-04-2015-
|
||
0024.
|
||
inal draft, Visualization, Validation, Software, Methodology, Investiga [19] P.L. Bannerman, A. Thorogood, Celebrating IT projects success: a multi-domain
|
||
tion, Formal analysis, Conceptualization. João Varajão: Writing – analysis, in: Proceedings of the 45th Hawaii International Conference on System
|
||
review & editing, Writing – original draft, Validation, Methodology, Sciences, Maui, HI, 2012.
|
||
[20] C. Barclay, K. Osei-Bryson, Determining the contribution of IS projects: an
|
||
Investigation, Data curation, Conceptualization.
|
||
approach to measure performance, in: Proceedings of the 42nd Hawaii
|
||
International Conference on System Sciences, Waikoloa, HI, 2009.
|
||
[21] R.L. Keeney, Value-Focused Thinking: A Path to Creative Decisionmaking, Harvard
|
||
Declaration of competing interest
|
||
University Press, 1992.
|
||
[22] R. Solingen, E. Berghout, The Goal/Question/Metric Method: A Practical Guide for
|
||
The authors declare that they have no known competing financial Quality Improvement of Software Development, McGraw-Hill, 1999.
|
||
[23] S. French, Decision Theory: An Introduction to the Mathematics of Rationality,
|
||
interests or personal relationships that could have appeared to influence
|
||
Ellis Horwood, 1986.
|
||
the work reported in this paper. [24] R. Göb, C. McCollin, M. Ramalhoto, Ordinal methodology in the analysis of Likert
|
||
scales, Qual. Quant. 41 (5) (2007) 601–626, https://doi.org/10.1007/s11135-007-
|
||
9089-z.
|
||
Acknowledgement
|
||
[25] S.S. Stevens, On the theory of scales of measurement, Science 103 (2684) (1946)
|
||
677–680, https://doi.org/10.1126/science.103.2684.677.
|
||
This work has been supported by FCT – Fundação para a Ciência e [26] W. Edwards, J.R. Newman, Multiattribute evaluation, in: T. Connolly, H.R. Arkes,
|
||
Tecnologia within the R&D Unit Project Scope UID/00319/2025 - K.R. Hammond (Eds.), Judgment and Decision Making: An Interdisciplinary
|
||
Reader, 2nd ed, Cambridge University Press, 2000, pp. 17–34.
|
||
Centro ALGORITMI (ALGORITMI/UM). João C. Lourenço acknowledges [27] R. von Nitzsch, M. Weber, The effect of attribute ranges on weights in
|
||
the financial support of Portuguese funds through FCT – Fundação para multiattribute utility measurements, Manag. Sci. 39 (8) (1993) 937–943, https://
|
||
a Ciência e a Tecnologia, I.P., under the project UID/97/2025 (CEGIST). doi.org/10.1287/mnsc.39.8.937.
|
||
[28] A. Basar, A novel methodology for performance evaluation of IT projects in a fuzzy
|
||
João C. Lourenço acknowledges the financial support of Portuguese environment: a case study, Soft Comput. 24 (14) (2020) 10755–10770, https://doi.
|
||
funds through FCT – Fundação para a Ciência e a Tecnologia, I.P., under org/10.1007/s00500-019-04579-y.
|
||
the project UID/97/2025 (CEGIST). [29] H.N. Ismail, Measuring success of water reservoir project by using delphi and
|
||
priority evaluation method, in: Proceedings of the IOP Conference Series: Earth
|
||
and Environmental Science 588, 2020 042021, https://doi.org/10.1088/1755-
|
||
Data availability 1315/588/4/042021.
|
||
[30] J.H. Yu, H.R. Kwon, Critical success factors for urban regeneration projects in
|
||
Korea, Int. J. Proj. Manag. 29 (7) (2011) 889–899, https://doi.org/10.1016/j.
|
||
The data is presented in the article. ijproman.2010.09.001.
|
||
[31] A. Nguvulu, S. Yamato, T. Honma, Project performance evaluation using deep
|
||
References belief networks, IEEJ Trans. Electron. Inf. Syst. 132 (2) (2012) 306–312, https://
|
||
doi.org/10.1541/ieejeiss.132.306.
|
||
[32] C. Wohlin, A.A. Andrews, Assessing project success using subjective evaluation
|
||
[1] R. Colomo-Palacios, I. González-Carrasco, J.L. López-Cuadrado, A. Trigo, J.
|
||
factors, Softw. Qual. J. 9 (1) (2001) 43–70, https://doi.org/10.1023/a:
|
||
E. Varajao, I-Competere: using applied intelligence in search of competency gaps in
|
||
1016673203332.
|
||
software project managers, Inf. Syst. Front. 16 (4) (2014) 607–625, https://doi.
|
||
[33] X. Yan, Utilizing the BSC method for IT performance evaluation of construction
|
||
org/10.1007/s10796-012-9369-6.
|
||
companies, in: Proceedings of the First International Conference on Information
|
||
[2] M.A. Kafaji, Interchange roles of formal and informal project management on
|
||
Science and Engineering, Nanjing, China, 2009.
|
||
business operational success, Prod. Plan. Control (2022) 1–21, https://doi.org/
|
||
[34] R.S. Kaplan, D.P. Norton, The balanced scorecard–measures that drive
|
||
10.1080/09537287.2022.2089265.
|
||
performance, Harv. Bus. Rev. 70 (1) (1992) 71–79.
|
||
[3] L.A. Ika, J.K. Pinto, The “re-meaning” of project success: updating and recalibrating
|
||
[35] C.L. Yang, R.H. Huang, M.T. Ho, Multi-criteria evaluation model for a software
|
||
for a modern project management, Int. J. Proj. Manag. 40 (7) (2022) 835–848,
|
||
development project, in: Proceedings of the IEEE International Conference on
|
||
https://doi.org/10.1016/j.ijproman.2022.08.001.
|
||
Industrial Engineering and Engineering Management, Hong Kong, China, 2009.
|
||
[4] B. Lobato, J. Varajão, C. Tam, A.A. Baptista, CrEISPS–a framework of criteria for
|
||
[36] T.L. Saaty, The Analytic Hierarchy Process: Planning, Priority Setting, Resource
|
||
evaluating success in information systems projects, Procedia Comput. Sci. 256
|
||
Allocation, McGraw-Hill, 1980.
|
||
(2025) (2025) 1821–1835, https://doi.org/10.1016/j.procs.2025.02.323.
|
||
[37] C.A. Bana e Costa, J.C. Vansnick, A critical analysis of the eigenvalue method used
|
||
[5] N. Agarwal, U. Rathod, Defining ‘success’ for software projects: an exploratory
|
||
to derive priorities in AHP, Eur. J. Oper. Res. 187 (3) (2008) 1422–1428, https://
|
||
revelation, Int. J. Proj. Manag. 24 (4) (2006) 358–370, https://doi.org/10.1016/j.
|
||
doi.org/10.1016/j.ejor.2006.09.022.
|
||
ijproman.2005.11.009.
|
||
[38] J.S. Dyer, Remarks on the analytic hierarchy process, Manag. Sci. 36 (3) (1990)
|
||
[6] R. Atkinson, Project management: cost, time and quality, two best guesses and a
|
||
249–258, https://doi.org/10.1287/mnsc.36.3.249.
|
||
phenomenon, its time to accept other success criteria, Int. J. Proj. Manag. 17 (6)
|
||
[39] P. Goodwin, G. Wright, Decision Analysis for Management Judgment, 5th ed., John
|
||
(1999) 337–342, https://doi.org/10.1016/S0263-7863(98)00069-6.
|
||
Wiley & Sons, 2014.
|
||
[7] H. Landrum, V.R. Prybutok, X. Zhang, The moderating effect of occupation on the
|
||
[40] V. Belton, T.J. Stewart, Multiple Criteria Decision Analysis: An Integrated
|
||
perception of information services quality and success, Comput. Ind. Eng. 58 (1)
|
||
Approach, Kluwer Academic Publishers, 2002.
|
||
(2010) 133–142, https://doi.org/10.1016/j.cie.2009.09.006.
|
||
[41] R.L. Keeney, D. von Winterfeldt, Practical value models, in: W. Edwards, R.
|
||
[8] J.K. Pinto, D.P. Slevin, Project success: definitions and measurement techniques,
|
||
F. Miles Jr., D. von Winterfeldt (Eds.), Advances in Decision Analysis: From
|
||
Proj. Manag. J. 19 (1) (1988) 67–72.
|
||
Foundations to Applications, Cambridge University Press, 2007, pp. 232–252.
|
||
[9] J. Varajão, L. Magalhães, L. Freitas, P. Rocha, Success management–from theory to
|
||
practice, Int. J. Proj. Manag. 40 (5) (2022) 481–498, https://doi.org/10.1016/j.
|
||
ijproman.2022.04.002.
|
||
|
||
|
||
13
|
||
J.C. Lourenço and J. Varajão Computer Standards & Interfaces 97 (2026) 104122
|
||
|
||
[42] J.S. Dyer, J.E. Smith, Innovations in the science and practice of decision analysis: [61] V. Henriquez, J.A. Calvo-Manzano, A.M. Moreno, T. San Feliu, Agile governance
|
||
the role of management science, Manag. Sci. 67 (9) (2020) 5364–5378, https://doi. practices by aligning CMMI V2.0 with portfolio SAFe 5.0, Comput. Stand.
|
||
org/10.1287/mnsc.2020.3652. Interfaces 91 (2025) (2025) 103881, https://doi.org/10.1016/j.csi.2024.103881.
|
||
[43] J.E. Smith, J.S. Dyer, On (measurable) multiattribute value functions: an [62] V. Ferretti, G. Montibeller, Key challenges and meta-choices in designing and
|
||
expository argument, Decis. Anal. 18 (4) (2021) 247–256, https://doi.org/ applying multi-criteria spatial decision support systems, Decis. Support Syst. 84
|
||
10.1287/deca.2021.0435. (2016) 41–52, https://doi.org/10.1016/j.dss.2016.01.005.
|
||
[44] J.S. Dyer, R.K. Sarin, Measurable multiattribute value functions, Oper. Res. 27 (4) [63] L.D Phillips, Decision conferencing, in: W. Edwards, R.F. Miles Jr., D. von
|
||
(1979) 810–822, https://doi.org/10.1287/opre.27.4.810. Winterfeldt (Eds.), Advances in Decision Analysis: From Foundations to
|
||
[45] R.L Keeney, Developing objectives and attributes, in: W. Edwards, R.F. Miles Jr., Applications, Cambridge University Press, 2007, pp. 375–399.
|
||
D. von Winterfeldt (Eds.), Advances in Decision Analysis: From Foundations to [64] T.Y. Chen, H.F. Chang, Critical success factors and architecture of innovation
|
||
Applications, Cambridge University Press, 2007, pp. 104–128. services models in data industry, Expert Syst. Appl. 213 (2023) 119014, https://
|
||
[46] B. Fasolo, C.A. Bana e Costa, Tailoring value elicitation to decision makers' doi.org/10.1016/j.eswa.2022.119014.
|
||
numeracy and fluency: expressing value judgments in numbers or words, Omega [65] C.M. Smith, D. Shaw, The characteristics of problem structuring methods: a
|
||
44 (0) (2014) 83–90, https://doi.org/10.1016/j.omega.2013.09.006. literature review, Eur. J. Oper. Res. 274 (2) (2019) 403–416, https://doi.org/
|
||
[47] C.A. Bana e Costa, E.C. Corrêa, J.M. De Corte, J.C. Vansnick, Facilitating bid 10.1016/j.ejor.2018.05.003.
|
||
evaluation in public call for tenders: a socio-technical approach, Omega 30 (3) [66] M. Marttunen, J. Lienert, V. Belton, Structuring problems for multi-criteria
|
||
(2002) 227–242, https://doi.org/10.1016/S0305-0483(02)00029-4. decision analysis in practice: a literature review of method combinations, Eur. J.
|
||
[48] R.L. Keeney, H. Raiffa, Decisions With Multiple Objectives: Preferences and Value Oper. Res. 263 (1) (2017) 1–17, https://doi.org/10.1016/j.ejor.2017.04.041.
|
||
Tradeoffs, John Wiley & Sons, 1976. [67] C.A. Bana e Costa, J.C. Lourenço, M.P. Chagas, J.C. Bana e Costa, Development of
|
||
[49] W. Edwards, F.H. Barron, SMARTS and SMARTER: improved simple methods for reusable bid evaluation models for the Portuguese Electric Transmission Company,
|
||
multiattribute utility measurement, Organ. Behav. Hum. Decis. Process. 60 (3) Decis. Anal. 5 (1) (2008) 22–42, https://doi.org/10.1287/deca.1080.0104.
|
||
(1994) 306–325, https://doi.org/10.1006/obhd.1994.1087. [68] D. Clegg, R. Barker, Case Method Fast-Track: A RAD Approach, Addison-Wesley
|
||
[50] C.A. Bana e Costa, J.C. Vansnick, MACBETH – An interactive path towards the Longman Publishing, 1994.
|
||
construction of cardinal value functions, Int. Trans. Oper. Res. 1 (4) (1994) [69] M. Weber, Decision making with incomplete information, Eur. J. Oper. Res. 28 (1)
|
||
489–500, https://doi.org/10.1016/0969-6016(94)90010-8. (1987) 44–57, https://doi.org/10.1016/0377-2217(87)90168-8.
|
||
[51] C.A. Bana e Costa, J.M. De Corte, J.C. Vansnick, MACBETH, Int. J. Inf. Technol. [70] C.A. Bana e Costa, P. Vincke, Measuring credibility of compensatory preference
|
||
Decis. Mak. 11 (2) (2012) 359–387, https://doi.org/10.1142/ statements when trade-offs are interval determined, Theory Decis. 39 (2) (1995)
|
||
S0219622012400068. 127–155, https://doi.org/10.1007/BF01078981.
|
||
[52] C.A. Bana e Costa, J.M. De Corte, J.C. Vansnick, On the mathematical foundations [71] L.D. Phillips, A theory of requisite decision models, Acta Psychol. 56 (1–3) (1984)
|
||
of MACBETH, in: S. Greco, M. Ehrgott, J.R. Figueira (Eds.), Multiple Criteria 29–48, https://doi.org/10.1016/0001-6918(84)90005-2.
|
||
Decision Analysis: State of the Art Surveys, Springer, 2016, pp. 421–463, https:// [72] J. Pereira, J. Varajão, N. Takagi, Evaluation of information systems project
|
||
doi.org/10.1007/978-1-4939-3094-4_11. success–insights from practitioners, Inf. Syst. Manag. (2021) 1–18, https://doi.org/
|
||
[53] W. Edwards, How to use multiattribute utility measurement for social 10.1080/10580530.2021.1887982.
|
||
decisionmaking, IEEE Trans. Syst. Man Cybern. 7 (5) (1977) 326–340, https://doi. [73] N. Takagi, J. Varajão, ISO 21502 and Success Management: A Required Marriage in
|
||
org/10.1109/TSMC.1977.4309720. Project Management, SAGE Open, 2025, pp. 1–11, https://doi.org/10.1177/
|
||
[54] D. von Winterfeldt, W. Edwards, Decision Analysis and Behavioral Research, 21582440251355046. July-September.
|
||
Cambridge University Press, 1986. [74] F.A.F. Ferreira, S.P. Santos, Two decades on the MACBETH approach: a
|
||
[55] C.W. Kirkwood, Strategic Decision Making: Multiobjective Decision Analysis with bibliometric analysis, Ann. Oper. Res. 296 (1) (2021) 901–925, https://doi.org/
|
||
Spreadsheets, Duxbury Press, 1997. 10.1007/s10479-018-3083-9v.
|
||
[56] L.I. Assalaarachchi, M.P.P. Liyanage, C. Hewagamage, A framework of critical [75] J. Varajão, L. Lopes, A. Tenera, Framework of standards, guides and methodologies
|
||
success factors of cloud-based project management software adoption, Int. J. Inf. for project, program, portfolio, and PMO management, Comput. Stand. Interfaces
|
||
Syst. Proj. Manag. 13 (2) (2025) e4, https://doi.org/10.12821/ijispm130204. 92 (2025) (2025) 103888, https://doi.org/10.1016/j.csi.2024.103888.
|
||
[57] N. Pinheiro, J. Vrajão, I. Moura, Success factors of public sector information [76] I.I. Mitroff, T.R. Featheringham, On systemic problem solving and the error of the
|
||
systems projects in developing countries, Sustain. Futures 10 (2025) (2025) third kind, Behav. Sci. 19 (6) (1974) 383–393, https://doi.org/10.1002/
|
||
101095, https://doi.org/10.1016/j.sftr.2025.101095. bs.3830190605.
|
||
[58] J. Jayakody, W. Wijayanayake, Critical success factors for DevOps adoption in [77] J. Varajão, Success Management as a PM knowledge area – work-in-progress,
|
||
information systems development, Int. J. Inf. Syst. Proj. Manag. 11 (3) (2023) Procedia Comput. Sci. 100 (2016) (2016) 1095–1102, https://doi.org/10.1016/j.
|
||
60–82, https://doi.org/10.12821/ijispm110304. procs.2016.09.256.
|
||
[59] K. Schwaber, J. Sutherland, The Scrum Guide - The Definitive Guide to Scrum: The [78] Y. Kong, N. Zhang, Z. Duan, B. Yu, Collaboration with generative AI to improve
|
||
Rules of the Game, scrumguides.org, 2020. https://scrumguides.org/docs/sc requirements change, Comput. Stand. Interfaces 94 (2025) (2025) 104013, https://
|
||
rumguide/v2020/2020-Scrum-Guide-US.pdf. doi.org/10.1016/j.csi.2025.104013.
|
||
[60] M. Jovanovic, A.L. Mesquida, A. Mas, R. Colomo-Palacios, Agile transition and
|
||
adoption frameworks, issues and factors: a systematic mapping, IEEE Access 8
|
||
(2020) (2020) 15711–15735, https://doi.org/10.1109/ACCESS.2020.2967839.
|
||
|
||
|
||
|
||
|
||